Application stages and statuses
Here is a summary of all the stages and statuses through which applications may pass. While building consent applications may pass through all these stages and statuses, supporting applications pass through only a subset.
Stages
Stage |
States |
Description |
---|---|---|
Draft |
Draft |
You can draft any number of applications in Objective Build. These are visible only to you or your organisation. The system assigns a unique BLD identification number to a new draft application. You can edit applications in the Draft state. |
Lodgement |
BCA checks your application is complete and lodges it into the BCA's system. |
|
Submitted |
When you start the submission process for an application, Objective Build locks the application to ensure the integrity of your application throughout the vetting and lodgement process. |
|
Submitting... |
Objective Build processes the application and passes it to the BCA system. |
|
Submit Failure |
The submit process failed. Check your notifications for more failure information. |
|
Vetting |
BCA performs an administrative check of your application for completeness. |
|
Vetting RFIs |
BCA requests you add additional information to your application. |
|
Accepted |
BCA accepts your application but it is not yet lodged in the BCA system. |
|
Lodged |
BCA lodges your application in the BCA system. |
|
|
BCA performs a technical assessment of your application for compliance with the Building Code and issues a consent. |
|
Processing |
BCA checks the documents you supplied show the proposed building work complies with the Building Code. |
|
RFIs |
BCA requires clarification or further information. |
|
Issued |
BCA is satisfied Building Code compliance is verified and you have paid all fees and levies. BCA grants the building consent. |
|
|
Consent informs you of inspections required for BCA to be satisfied the building work complies with the consent and Building Code. |
|
In Progress |
Number of inspections in progress |
|
Completed |
Number of inspections completed |
|
Failed |
Number of inspections that failed |
|
|
You apply for a code compliance certificate with the required supporting documents. BCA issues the certificate if the building work complies with the building consent. |
|
CCC Started |
Your application for code compliance certificate is accepted and the CCC process started. |
|
CCC Processing |
BCA processes your CCC application to determine the building work is compliant. |
|
CCC Issued |
BCA is satisfied with Building Code compliance and issues the certificate. |
Statuses
Status |
Description |
---|---|
|
Not started |
|
Started, in progress |
|
Suspended: you have an action to complete, such as responding to a request for information |
|
Awaiting Payment |
|
Completed |
|
Rejected, Refused or Withdrawn |
|
Locked: a submitted application is locked as read-only |